2019
Bormioli Rocco - Altare
Demolition, reconstruction and start up of furnace 1
Saint Gobain - Calarasi Float
Hot works during Float reconstruction
Bormioli Pharma - San Vito
Furnace project, carpentry, plants engineering. Demolition, reconstruction and start up of furnace SV2
Bormioli Pharma - Bergantino
Furnace, carpentry and plants engineering. Demolition, reconstruction and start up of furnace BR1
2020
Bormioli Pharma - San Vito
Demolition, reconstruction and start up of furnace SV1
Bormioli Luigi - Parma
Full reconstruction, supply of plants, refractory and carpentry.
Technoglas Gmbh - Austria
Full reconstruction, pre-heating and start up
Zignago Vetro - Empoli
Partial reconstruction, carpentry supply, controlled cooling, pre-heating and start up.
Eurofibre S.p.A. Marcon
Complete design of the furnace for the requalification of internal cullet. Innovative project of submerged Combustion Melter.
2021
Bormioli Pharma S.p.A. Bergantino
Furnace BG1: complete reconstruction, (plants, refractory materials, steel structures), supply of steel structures, refractory materials and equipment, pushing and sealing of electrodes. Heat-up and start-up of the furnace.
Saint Gobain Pisa
Complete overcoating and sealing of float furnace.
Bormioli Rocco S.p.A. Altare
Forehearth 11 at F1 Altare: demolition (refractory materials, steel structures), reconstruction (refractory materials, steel structures) and heat-up.
Bormioli Rocco S.A. Azuqueca
Forehearth 24 at F2 : demolition (refractory materials, steel structures), reconstruction (refractory materials, steel structures) and heat-up.
Vetrerie Riunite Verona
Forehearth 10: design of refractory materials, steel structures and plants, supply and installation of plants, refractory materials, and steel structures. Heat-up and start-up.
2022
Bormioli Pharma S.p.A. San Vito
Furnace Sv1: steel and refractories engineering for furnace and forehearths.
Bormioli Pharma S.p.A Bergantino
Furnace BG3: equipment and steel engineering. Demolition and partial reconstruction of equipment, refractories and carpentries. Steel, equipment and refractories supply, draining, preheating and start up (July 2022)
Verallia Italia S.p.a. Dego
Furnace 13: demolition, reconstruction (refractories, carpentries), steel supply.
Vetrerie Riunite Verona
Furnace 2: refractories, steel and equipment engineering. Demolition, supply and erection of equipment, carpentries and refractories, preheating and start-up.
Bormioli Pharma S.p.A.San Vito
Furnace SV1: refractories demolition and draining.
Vetrerie Riunite Verona
DENOX system: complete engineering, equipment supply and start up
Bormioli Rocco Fidenza
Furnace 10: 1) engineering of civil works, carpentries and 3 IS machines positioning. 2) demolition, reconstruction (refractories, steel), equipment and steel supply, draining, preheating and start-up.
Vetreria Etrusca Altare
Furnace 2: complete engineering of the new furnace (equipment, refractories, carpentries).